On one hand, this project feels like it’s taking forever (2 years and counting since we first shared our concept with our neighbours), but on the other, I’m not sure we’d be able to handle it if it moved any faster, what with the rest of life and all. We’re currently looking at a construction start of early 2018 and there’s a lot that has to happen before then!
At the Committee of the Whole meeting in August, Council voted 7 to 1 that our project was ready to go to public hearing. So mark your calendars for November 9, folks! This is the day we present to Council and the public, and anyone with an opinion is welcome to speak. After that, council weighs in and then votes yes or no to our application. If they vote yes, then we’re done with the rezoning part and can focus on getting to construction. If they vote no, it’s back to the drawing board.
Our general plan is that we be ready to submit for building permit as soon after the public hearing as possible. Once we have our building permit, we can start construction.
Here’s the “lot” that has to happen next:
- Finish the passive house model to a point that our certifier can review it and flag anything big before we apply for our building permit.
- Find a structural engineer to look at our renovation plans, as well as any strange lateral loads we are introducing by attaching a second house to the side of our current house. Last time I called around, half my calls went unanswered, and the other half said they were too busy to take on any more work. This input will be a requirement for our building permit.
- Meet with Mark A (our architect) and Russ (our builder) to firm up our assemblies and talk about cost and constructability issues. The big one currently on my mind is how we will insulate a hip roof transitioning to a flat roof. We’d like to do exterior insulation, but how realistic/affordable/buildable will this be?
- This meeting should give Russ what he needs to work up a construction budget, which we can then use to secure financing (another big looming question that I look forward to resolving very soon!).
- Prepare for and present at the public hearing.
- Prepare building permit drawings and apply for building permit.
- Find a place to live during construction, pack up and move there!
- Clear out as much of our existing house as we can before Russ takes over.
As for the rest of life, there’s work, hosting Thanksgiving dinner, celebrating our anniversary, visiting friends in Toronto, watching a few movies, hanging out with family and friends, riding bikes, sleeping, eating, reading, being healthy…no big deal, right?
Kate says
Brilliant! So happy to hear about the progress. I think you have almost reached the (first) finish line. Well done.
clove says
Thank you for the encouragement, Kate! Little by little…